0014 — Task plan and checkpoints

  • Status: Implemented (step 11.7, unreleased). Shipped behaviour: SPEC; tools: MCP tools → Plan.
  • Size: ~2 agent-days (model, migration and service ~0.75; hooks, todo and reminders ~0.5; MCP, board and docs ~0.75).

Problem

An agent should always work by a plan the owner can see. A report at the end of a stage says what happened, not what was meant to happen, and nothing shows a drift while the work goes on. Claude Code keeps its own todo list, but it lives inside one context, disappears with /clear and is not something the owner accepted.

Model

  • Plan on the task: ordered plan_step rows (title, "what and why" markdown, status pending / in_progress / done / blocked). A done step is a checkpoint: done_at, a link (a report of the task or a PR URL), a one-line outcome and a conformance line, either as planned or deviation: <why> (required for done). Deviations are highlighted on the card and in the Plan tab.
  • Plan status on the task row: none (no steps), draft, accepted (with who and when). The owner accepts on the board, the coordinator with plan_accept. A change of the step titles or their order turns an accepted plan back to draft; status changes and "what and why" edits do not.
  • History: every plan write adds a plan_revision row with the whole plan as JSON, the author and a reason; the board shows them with the diff of the titles.
  • Task size: an optional size field (S / M / L), editable like the other fields; the first report whose first line names a size sets it when the task has none.
  • Second layer, never merged: the agent's Claude Code todo (session_todo, per relaybay session and Claude Code id) shows under the current plan step as "now doing: …" with the list collapsed. A task with no plan steps shows the todo marked "Agent's plan, not accepted".

Rules

A new requirement kind in the rules document: {"kind": "plan_accepted", "unless_size": ["S"]}, in the default stage_requirements.dev. A task of unknown size needs the plan. warn mode adds a warning to the move (a draft plan: "the plan is not accepted yet"); strict refuses it. A move to dev with neither plan steps nor a todo also adds a soft hint: "write down what you are going to do (todo or 2-3 steps with plan_set)".

Hooks

  • Todo capture. Checked live on Claude Code 2.1.309: the todo tools are off by default (desktop and CLI); with the env CLAUDE_CODE_ENABLE_TODO_TOOLS=1 they are TaskCreate (tool_input subject, description, activeForm; tool_response {"task": {"id", "subject"}}) and TaskUpdate (tool_input taskId, status; tool_response with statusChange: {from, to}). Older builds use TodoWrite with the whole list (todos: [{content, status, activeForm}]). relaybay reads all three from PostToolUse, before the activity coalescing, so no change is lost; unknown shapes are ignored and sizes capped (50 items, 200 characters). A new Claude Code id (after /clear) starts a fresh list; a list written before the agent linked its hook session moves with the exact link.
  • Reminder. For an exactly linked session (cc_exact) and its bound open tasks: the current step (N/M, title, "what and why") and the todo item in progress go into additionalContext on SessionStart, after a todo change and every plan_reminder_every tool events (default 30), never the same text twice in a row (a new SessionStart is a new context). Owner comments in the same answer keep the rest of the 8000-character budget.

API

plan_get(task), plan_set(task, steps, reason?) (replace semantics like review_steps_set: step N keeps status and checkpoint while its title stays), plan_step_update(task, step, status, outcome?, link?, conformance?), plan_accept(task); task_update gains size. Events plan.set, plan.step_updated, plan.accepted, session.todo_updated.

Decided by default

  • relaybay setup does not write CLAUDE_CODE_ENABLE_TODO_TOOLS: it is the user's choice and easy to add or remove in Claude Code's settings.
  • Plan writes that change nothing (same titles and details, same status and checkpoint) are not kept as revisions.
  • Leaving done clears the checkpoint; marking a done step done again (a new outcome or conformance) keeps its done_at.
  • A plan step's text is details in plan_set, as in review_steps_set.
  • A link is a report of the same task (12, #12, report:12, stored as report:12) or an http(s) URL; anything else is refused.
  • Agents do not accept plans; plan_accept is meant for the coordinator.
  • Reminders count PostToolUse events only; 0 turns the periodic reminder off.
  • The card shows the plan, not the todo; the todo is in the Plan tab.

Living plan (0.7)

On a real task the plan was 3/3 done in draft while rework went on by the owner's decisions: the plan could not grow without losing its acceptance and nobody was told to add a step. The plan is a map of where the work goes and where it is, for the owner and the agent, all the way.

  1. plan_step_add(task, title, details?, reason) appends a pending step. The plan's status stays as it is; on an accepted plan the step carries added_after_acceptance_at, added_by and added_reason (migration 0022), shown in the Plan tab and in the history diff as + 4. title (added after acceptance). A plan_revision with the reason and plan.step_added. reason is required. plan_set keeps its rule: changed titles or order make a draft.
  2. Server instruction 11: a change or an addition after a report is a new step with plan_step_add (or the step back to in_progress), the stage back to dev, progress and next_step updated.
  3. The stage follows the plan. plan_step_add, and plan_step_update taking a done step back to in_progress, on a task in review or test move it to dev in the same transaction with the stage note rework: <reason> (a reopened step: rework: <its title>) and the usual task.stage_changed; the answer says <key> moved from review back to dev (rework: …).. When a plan_step_update makes every step done on a task in dev that has review steps, the answer adds Hint: all steps done and the review checklist is set: move the task to review (task_set_stage). Nothing moves to review by itself.
  4. Closed-plan warning. On a task whose plan steps are all done and a report came strictly after the plan closed (the newer of the newest done_at and the newest plan revision, so a plan_set dropping the last open step closes it too), report_add adds Warning (rules): the plan is closed (N/N done) while work goes on: add a step with plan_step_add or reopen one. when the state is changed in any open stage (code changed after the plan closed, e.g. rework in review) or verified in dev; a task_update / task_patch changing progress adds it only in dev, behind the same gate. The closing report and the closing progress never warn. A warning in strict mode too, never a refusal. The reminder and the session-start context say Plan of <key> (<state>): the plan is closed (N/N done) … only for a task in dev; other stages keep "all N steps done". plan_step_add on a done task is refused ("reopen it (task_set_stage) before adding steps"); on live it is allowed and the answer says the step does not move the task.
  5. Draft hint. A task in dev whose plan is a draft and whose newest plan revision is at least plan_draft_hint_hours old (default 1, 0 off): portfolio_digest, project_digest and task_context end with Hint: <key>'s plan is a draft for N h: accept it (plan_accept) or ask for changes. only when the caller is a coordinator session (named in coordinators, checked before the call links its hook session); project_snapshot has no caller identity and never carries it. Oldest first, at most five lines, then …and N more drafts.; the query finds only those tasks. The card's Plan badge shows draft · N h. Never a line for the agent.

Decided by default:

  • Only a step added to an accepted plan is marked; on a draft plan (or a task without a plan, which then gets a draft) plan_step_add is a plain append with the reason in the history.
  • A step renamed by plan_set loses its mark, like its checkpoint.
  • The automatic move back to dev runs no stage rules (the plan's own write decides it) and does not mention the pulse.
  • The rework and all-done lines are MCP answer notes, not rule warnings; the closed-plan warning is a note too, so the owner's board form never shows it.
  • The all-done hint comes only from the update that closes the plan (a done step marked done again says nothing).
  • N in the draft hint is whole hours, rounded down; the hint lines are appended at the end of the digest text, after its budget.
  • "After the plan closed" is strictly later: a report in the same millisecond as the closing write does not count.

Todo capture on Claude Code 2.1.318 (checked live with CLAUDE_CODE_ENABLE_TODO_TOOLS=1): TaskCreate and TaskUpdate (status with or without activeForm) are recorded and "Now doing" shows under the current step; the parser needed no change. Known limit: the forwarder gives up after 0.3 s per network step and stays silent, so a dropped hook loses that todo change until the next one (seen once: a status-only TaskUpdate about 30 s after the create stayed pending until the next update).

Risks

Risk Mitigation
Todo tool payloads change between Claude Code builds Defensive parsing, unknown shapes ignored, both generations supported
Reminders crowd the agent's context Only on start, todo change and every N tools; never the same text twice; capped length
The plan turns into ceremony for small tasks S tasks need no accepted plan; the todo counts as the agent's plan